Project Management Professional (PMP) Exam Practice – Question1040

When cost variance is negative and schedule variance is positive, the project is:


A.
under budget and behind schedule.
B. over budget and ahead of schedule.
C. on schedule.

D. complete; all planned values have been earned.

Correct Answer: B