Project Management Professional (PMP) Exam Practice – Question1042

How is quality control performed?


A.
By identifying quality standards that are relevant to the project and determining how to satisfy them
B. By monitoring specific project results in compliance with relevant quality standards and determining corrective actions as needed
C. By ensuring that the entire project team has been adequately trained in quality assurance processes
D. By applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards

Correct Answer: B