Project Management Professional (PMP) Exam Practice – Question1046

Which knowledge area employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?


A.
Project Risk Management
B. Project Integration Management
C. Project Communications Management
D. Project Quality Management

Correct Answer: C