Project Management Professional (PMP) Exam Practice – Question1052

Cost aggregation is typically performed by aggregating work packages in accordance with the:


A.
Program evaluation and review technique (PERT).
B. Cost of quality (COQ).
C. Rough order of magnitude (ROM).
D. Work breakdown structure (WBS).

Correct Answer: D