Project Management Professional (PMP) Exam Practice – Question1054

Which of the following are outputs of the Monitor and Control Project Work process?


A.
Requested changes, forecasts, recommended corrective actions
B. Forecasts, resources plan, bottom up estimating
C. Recommended corrective actions, cost baseline, forecasts
D. Requested changes, recommended corrective actions, project constraints

Correct Answer: A