Project Management Professional (PMP) Exam Practice – Question1057

As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?


A.
BAC
B. EAC

C. ETC
D. WBS

Correct Answer: B