Project Management Professional (PMP) Exam Practice – Question1060 The cost performance baseline is typically displayed in the form of: A. An S-curve. B. A normal curve. C. A U-curve. D. A positive slope line. Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question1059Project Management Professional (PMP) Exam Practice – Question1061