Project Management Professional (PMP) Exam Practice – Question1061 What happens to a stakeholders project influence over time? A. Increases B. Decreases C. Stays the same. D. Has no bearing. Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question1060Project Management Professional (PMP) Exam Practice – Question1062