Project Management Professional (PMP) Exam Practice – Question1062

Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?


A.
Performance organizations
B. Schedule baselines
C. Performance measurements
D. Change requests

Correct Answer: C