Project Management Professional (PMP) Exam Practice – Question1067 Which technique is utilized in the Schedule Control process? A. Performance Measure B. Baseline Schedule C. Schedule Comparison D. Variance Analysis Show Answer Hide Answer Correct Answer: D Post navigation Project Management Professional (PMP) Exam Practice – Question1066Project Management Professional (PMP) Exam Practice – Question1068