Project Management Professional (PMP) Exam Practice – Question1073

Cost variance (CV) is equal to earned value:


A.
Minus actual cost [EV -AC].
B. Minus planned value [EV -PV].
C. Divided by actual cost [EV/AC].
D. Divided by planned value [EV/PV].

Correct Answer: A