Project Management Professional (PMP) Exam Practice – Question1079

Which of the following are the components of the scope baseline?


A.
Project charter, project scope statement, and work breakdown structure (WBS)
B. Project charter, project management plan, and plan procurement
C. Project scope statement, work breakdown structure (WBS), and WBS dictionary
D. Project management plan, plan procurement, and contract administration

Correct Answer: C