Project Management Professional (PMP) Exam Practice – Question1085 The CPI is .92, and the EV is US$172,500. What is the actual cost of the project? A. US$158,700 B. US$172,500 C. US$187,500 D. US$245,600 Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question1084Project Management Professional (PMP) Exam Practice – Question1086