A project is being audited, and the project manager receives numerous comments and questions from an unfamiliar person in the company. The project manager shares this information with team members, none of whom know this person. The project manager
is unsure how to manage this situation.

What should the project manager do first?


A.
Review the responsible, accountable, consult, and inform (RACI) matrix.
B. Respond to the persons comments and questions.
C. Check the stakeholder register.
D. Review the work breakdown structure (WBS).

Correct Answer: A