Project Management Professional (PMP) Exam Practice – Question1089

A set of high-impact, repetitive tasks must be executed during a project. What can the project manager use to ensure that all team members consistently perform these tasks in the same manner?


A.
Quality metrics
B. Quality controls
C. Quality audits
D. Quality checklists

Correct Answer: D