Project Management Professional (PMP) Exam Practice – Question1096

During a review meeting, the project manager realizes that scheduled quality control inspections were not conducted. Since the project is running short on time, the project manager decides to hold a joint customer acceptance inspection.
What should the project manager do next?


A.
Advise the team to ensure that all specifications are maintained so the client accepts the deliverable.
B. Create a nonconformance report and initiate a corrective action with the project team.
C. Keep the customer informed and seek approvals.
D. Issue a change request to extend the project schedule to complete the quality checks on time.

Correct Answer: C