Project Management Professional (PMP) Exam Practice – Question1098

A project manager must track schedule variances over time. What tool or technique should be used to determine whether or not the variances are within acceptable limits?


A.
Cause-and-effect diagram
B. Control chart
C. Scatter diagram
D. Control panel diagram

Correct Answer: B