Because a project is behind schedule, the sponsor suggests reducing the time for quality assurance testing. What should the project manager do?


A.
Perform quality control measurements.
B. Follow the quality management plan.
C. Perform quality audits.
D. Change the quality requirements.

Correct Answer: D