Project Management Professional (PMP) Exam Practice – Question1101

During a status meeting, a stakeholder requests a new requirement that was previously unidentified. What should the project manager do?


A.
Deny the request
B. Perform a risk analysis.
C. Implement the change and update the project management plan.
D. Execute the Perform Integrated Change Control process.

Correct Answer: B