Project Management Professional (PMP) Exam Practice – Question1102

A project manager, the project team, and stakeholders meet to discuss and resolve project issues. What process does this describe?


A.
Control Scope
B. Validate Scope
C. Manage Communications
D. Direct and Manage Project Work

Correct Answer: D