Project Management Professional (PMP) Exam Practice – Question1104

A project manager completes the requirements traceability matrix but indicates that not all requirements will be addressed. What should the project manager do to resolve this situation?


A.
Compile requirements through affinity diagrams.
B. Define the scope by using facilitation.
C. Plan scope management using expert judgement.
D. Control the scope through variance analysis.

Correct Answer: D