Project Management Professional (PMP) Exam Practice – Question1105

A project manager discovers a significant flaw in a major project deliverable. Which project management process is being performed?


A.
Manage Quality
B. Control Quality
C. Plan Quality Management
D. Statistical Sampling

Correct Answer: B