Deliverables are being validated prior to client handoff. Quality team members find some defective parts and send them for rework by the assembly line team.
Under what cost of quality (COQ) classification does this fail?


A.
Cost of nonconformance
B. Cost of conformance
C. Quality control cost
D. Quality measurement costs

Correct Answer: A