A project manager identifies the root cause of a quality issue and implements corrective action. What should the project manager do next?
A. Conduct an inspection of the issue.
B. Update the lessons learned documentation.
C. Revise the checksheets and organize the facts.
D. Perform a variance analysis.
A. Conduct an inspection of the issue.
B. Update the lessons learned documentation.
C. Revise the checksheets and organize the facts.
D. Perform a variance analysis.