Project Management Professional (PMP) Exam Practice – Question1110

A vendor who historically has not had quality issues, is delivering low-quality parts. The project manager is concerned that this will cause a delay due to rework.
What tool or technique should the project manager use to address this?


A.
Performance reporting
B. Procurement control system
C. Performance reviews
D. Contract change control system

Correct Answer: B