Project Management Professional (PMP) Exam Practice – Question1111

During a multiple-year project, the client and contractors have differing opinions on the projects deliverables, schedule, and quality. What should the project manager do to resolve this conflict?


A.
Review the project management plan with the client.
B. Develop the project schedule and ensure that the client agrees to it.
C. Ensure that the client approves the quality management plan.
D. Meet with the project team to discuss the deliverables.

Correct Answer: C