As a result of negative client feedback, a project manager is replaced midway through a project. The new project manager needs to compare stakeholders current attitudes to their original support for the project.
What will help the project manager with this task?
A. Stakeholder engagement assessment matrix
B. Requirements traceability matrix
C. Stakeholder register
D. Interpersonal skills
What will help the project manager with this task?
A. Stakeholder engagement assessment matrix
B. Requirements traceability matrix
C. Stakeholder register
D. Interpersonal skills