Project Management Professional (PMP) Exam Practice – Question1114

A project manager wants to establish a benchmark for comparing actual project performance with the project management plan. What process should the project manager complete to generate this model?


A.
Develop Project Charter
B. Sequence Activities
C. Develop Schedule
D. Create WBS

Correct Answer: B