A projects earned value (EV) report indicates that an activitys cost variance (CV) is -5,000 and its schedule variance (SV) is 1,000. What is the status of this activity?


A.
Behind schedule and over budget
B. On schedule and within budget
C. Behind schedule and within budget
D. Ahead of schedule and over budget

Correct Answer: D