Project Management Professional (PMP) Exam Practice – Question1122

A project management office (PMO) asks a project manager to calculate a projects contingency reserves. What should the project manager do?


A.
Review the risk management plan.
B. Check the total cost and add a reserve to cover quality issues.
C. Ask the PMO to increase the budget according to company policies.
D. Add a percentage to the cost based on previous experiences.

Correct Answer: A