Project Management Professional (PMP) Exam Practice – Question1123

A client adds a new feature and requests a budget update. The development of this feature cannot extend the project schedule for more than one month. The client has already agreed to a cost per hour.
What should the project manager do next?


A.
Calculate project performance using the earned value management (EVM) method.
B. Estimate the required number of additional project resources.
C. Update the resource management plan.
D. Review the responsibility assignment matrix (RAM).

Correct Answer: A