Project Management Professional (PMP) Exam Practice – Question1125

A novice project manager with limited knowledge of the construction industry is preparing to conduct a quarterly project review meeting. What should the project manager use as a framework to facilitate the meeting and to communicate information that includes
schedule, risk, performance, and budget?


A.
Scope management plan
B. Work breakdown structure (WBS)
C. Requirements management plan
D. Work performance reports

Correct Answer: D