A project manager is assigned to an ongoing project and receives notification from another department that they were not made aware of timeline slippage on one of the key deliverables. To which document should the project manager first refer?


A.
Project management plan
B. Risk matrix

C. Communications management plan
D. Project charter

Correct Answer: C