A project team member discovered an issue with the system being developed. The project manager learns that the team member fixed the issue without consulting the change control board (CCB).
What should the project manager do?


A.
Request additional funds to train the team member.
B. Determine if the documentation has been updated by the CCB.
C. Submit a change request to the CCB.
D. Remove the team member from the project.

Correct Answer: B