Project Management Professional (PMP) Exam Practice – Question1129

Key stakeholders disagree about the details in the project charter that describe how to deliver project requirements. What tool or technique should the project manager use to resolve this issue and obtain project charter approval?


A.
Expert judgement
B. Facilitation
C. Focus groups
D. Decision making

Correct Answer: B