Project Management Professional (PMP) Exam Practice – Question1130

A project manager has been keeping stakeholders informed about an unforeseen issue that caused a production delay. The issue is resolved, but a key stakeholder is dissatisfied because the product was delivered late.
What should the project manager have done to avoid this?


A.
Continuously updated the stakeholder engagement plan
B. Created more communication styles with which to update stakeholders
C. More frequently notified stakeholders or project changes
D. Obtained stakeholder feedback on the changes

Correct Answer: D