Project Management Professional (PMP) Exam Practice – Question1131

A project manager has a resource assigned to their project who lacks the necessary experience to complete the required tasks. What should the project manager do?


A.
Ask the project sponsor to reassign the resource.
B. Update the project team assignments.

C. Work with the resource to train and bridge the performance gap.
D. Ask an experienced team member to mentor this resource.

Correct Answer: B