Project Management Professional (PMP) Exam Practice – Question1132

Without consulting the project manager, a functional manager removes key project resources in order to assign them operational tasks. Since these resources are now focused on operational tasks rather than deliverables, the deliverables run late.
What should the project manager do first?


A.
Extend the project timeline.
B. Escalate the functional managers actions to the sponsor.
C. Negotiate time allocation to prioritize the resources workload.
D. Ask to have the resources replaced immediately.

Correct Answer: C