Project Management Professional (PMP) Exam Practice – Question1133

A company has a history of implementing system integration projects using their in-house software with a vendor hardware infrastructure. A project manager, new to the company, has no prior experience with vendor integration projects.
What should the project manager do?


A.
Refer to the project statement of work (SOW).
B. Review the project charter.
C. Seek expert judgement.
D. Meet with the sponsor.

Correct Answer: C