Project Management Professional (PMP) Exam Practice – Question1134

During a team review, the project manager learns that the schedule performance index (SPI) is 0.8 and the cost performance index (CPI) is 0.7. The project manager asks team members to work overtime.
How will this affect the CPI?


A.
It will decrease.
B. It will remain the same.
C. It will increase.
D. It will return to 1.0

Correct Answer: A