A project sponsor constantly asks the project technical lead for project information. To prevent this issue from continuing, what should the project manager do?


A.
Hold a one-to-one meeting with the project sponsor.

B. Send an updated stakeholder engagement plan to the technical lead.
C. Provide an updated communications management plan to all stakeholders.
D. Email all stakeholders requesting that they contact the project manager directly with questions.

Correct Answer: C