Project Management Professional (PMP) Exam Practice – Question1137

During a weekly progress meeting, a stakeholder announces that they are no longer able to cooperate with the project management team in obtaining the required government permits for construction. What should the project manager do first?


A.
Discuss the issue with the project sponsor.
B. Update the issue log and inform other stakeholders.
C. Exclude the activities that require the permits from the scope of work.
D. Assume the responsibility of obtaining the permits.

Correct Answer: B