As a project approaches its final phase, the project manager sends a follow-up report to the stakeholders. Some stakeholders comment that some unresolved issues have been excluded from the report.
What should the project manager have done to prevent this?


A.
Conducted the Monitor Communications process
B. Implemented the Monitor Risks process
C. Followed the Perform Integrated Change Control process
D. Better controlled project documents

Correct Answer: A