A project manager learns of concerns regarding the quality of the project team's engineering process requirements. Stakeholders believe that the team has failed to adhere to organizational standards. Most requirements are written after product testing.
What should the project manager do to confirm the quality of the process?


A.
Prepare a checklist for each of the requirement's deliverables.
B. Conduct peer reviews for each of the requirement's deliverables.
C. Review the work performance reports for the project team.
D. Develop a histogram to show the frequency of noncompliance.

Correct Answer: A