A company has recurring quality issues with one of its sole-source suppliers. A new project will incur significant penalties from the customer if deliveries are late.
What should the project manager do?


A.
Review incoming inspection reports and quality logs.
B. Negotiate with other vendors with better quality-control methods.
C. Identify high-level risks prior to developing contingency plans.
D. Escalate the issue to senior management.

Correct Answer: D