Project Management Professional (PMP) Exam Practice – Question1145

During a project team meeting, a team member suggests an enhancement that falls outside of the project charter. The project manager states that the team needs to concentrate on completing all required work.
Which action has the project manager performed?


A.
Scope creep
B. Change management
C. Conflict resolution
D. Scope management

Correct Answer: A