Project Management Professional (PMP) Exam Practice – Question1146

The project sponsor is inappropriately requesting status reports from individual team members. The project manager plans to meet with the sponsor to discuss the issue.
To what should the project manager refer prior to the meeting?


A.
Communications management plan
B. Risk management plan
C. Project charter
D. Work performance reports

Correct Answer: A