During an IT hardware manufacturing project, the project manager discovers that certain batches of components are failing quality inspections. What should the project manager use to lower the failure rate?


A.
Control chart
B. Tornado diagram
C. Probability and impact matrix
D. Fishbone diagram

Correct Answer: D