Project Management Professional (PMP) Exam Practice – Question1148

Midway through implementation of a construction project, a supplier fails to deliver cement and jeopardizes the project schedule. The construction team leader asks the project manager to implement a contingency plan.
What action should the project manager take?


A.
Inform project stakeholders of the risk occurrence.
B. Implement a workaround.
C. Refer to the risk register.
D. Brainstorm with the team

Correct Answer: A