While reviewing a status report, a project manager notices that, over a period of six months, the coding quality for one developer is statistically lower than another developer assigned the same task. Which tool should the project manager use to trace the
problem's source back to its actionable root cause?


A.
Histogram
B. Control chart
C. Scatter diagram
D. Ishikawa diagram

Correct Answer: D